E-prescribing Regulations

This is a hypothetical scenario, where an electronic medical record company is faced with additional regulatory requirements (additional data in e-prescriptions, real-time benefit checks, PA steps) and customer demands.

First let’s ask some questions:

  • How many other customers have raised this request?
  • What’s the contract impact of these customers?
  • How likely do we think we are to them churning if we don’t meet these needs?
  • What does success look like for this customer?
  • What constraints do we face in delivering it? (3rd party data providers, their timelines for giving us access, engineer capacity, QA)
  • Who actually chases PAs, and what does it cost them today?

At this point we have a tension, pull forward some work for a specific customer vs. keeping the development plan.

A few options and tradeoffs:

  1. Build it early. This might not be feasible depending on how the 3rd party data provider can manage certification slots.
  2. Continue with roadmap plan. Low risk and aligned to 2028, but nothing for the customer in the near term.
  3. Continue with plan and evaluate light lift interim. The lift would be a PA status view that could be manually updated, maybe enhance with additional data if the API provided that. A spike with the eng lead confirms that’s an option.

Evaluate the above options on: technical feasibility, tech debt, customer satisfaction, patient safety risk.

Based on the above : Option 3, contingent on the spike. If there’s no safe interim, fall back to option 2 with a dated plan for the customer. I’d change course if the customer says 3 months is a hard ultimatum or the 3rd party provider says they can’t provide us a cert.

Success metric: Time spent chasing PA status, + status accuracy.

Communicate

AudienceMessage
CustomerWhat you get at month 3, what comes after, and why
PM / engRecommendation, risks, spike scope
Prescribers and PA coordinatorsWhat changes in their workflow and when
Clinical and QASafety review scope and timing, before design is locked
DesignHandling “no status available” for insurers that don’t respond electronically
Account managersOne consistent story for the customer
LeadershipRoadmap tradeoff and renewal risk

At the end the path of delivering a lightweight version at month 3, sequence the work dependent on the certification slots, align everything to the 2028 requirement, and tell each audience exactly what changes for them and when – is the path I’d choose going forward!